How do change orders impact project cost and schedule?

Prepare for the NCARB Project Development and Documentation (PDD) Exam with targeted quizzes. Use our comprehensive flashcards and multiple-choice questions to master key concepts. Test your knowledge with hints and explanations to ensure success!

Multiple Choice

How do change orders impact project cost and schedule?

Explanation:
Change orders primarily change the scope of work, and that shift drives changes to both cost estimates and the project schedule. When the scope is altered—different quantities, different materials, or new tasks—the amount of work, materials, and labor required changes, which in turn changes the estimated cost and the time needed to complete the project. Because these impacts alter the project’s baseline, they require formal owner approval and an updated schedule and budget (revised baselines). Payment timing can be affected as a result of the new contract sum and milestones, but the essential effect of a change order is the change in scope that cascades into cost and schedule adjustments. The other options misstate the issue: change orders are not just about payment terms, and they do impact the schedule and are more than administrative tasks.

Change orders primarily change the scope of work, and that shift drives changes to both cost estimates and the project schedule. When the scope is altered—different quantities, different materials, or new tasks—the amount of work, materials, and labor required changes, which in turn changes the estimated cost and the time needed to complete the project. Because these impacts alter the project’s baseline, they require formal owner approval and an updated schedule and budget (revised baselines). Payment timing can be affected as a result of the new contract sum and milestones, but the essential effect of a change order is the change in scope that cascades into cost and schedule adjustments. The other options misstate the issue: change orders are not just about payment terms, and they do impact the schedule and are more than administrative tasks.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy